Ongoing Projects

These projects are currently in progress.

Turtle Creek Subsystem 3 Gravity

House numbers 122, 126, 128, 130 and 132 on SE Country Club Drive are scheduled to have a gravity system installed.

A contract for engineering design, permitting, bidding and construction services was awarded to Holtz Consulting.  The Contract has been bid and awarded to Giannetti Contracting Corp.  Giannetti has recently completed construction of the Jupiter Inlet Colony sewer/water/stormwater systems.  Work was started the first week of December 2017 and is proceeding in conjunction with Subsystem 2 construction.

Turtle Creek Subsystem 2 (West area) Gravity

Residents were polled for preference of a gravity or low pressure sewer system.  A majority of respondents did prefer gravity.

A Notice of Intent to Assess for a gravity sewer system to be provided to this area was approved by the Governing Board at the October, 2016 regular board meeting.

A contract for engineering services was awarded to Holtz Consulting Engineers. Engineer representatives will be on-site regularly to respond to construction issues.

The Contract has been bid and awarded to Giannetti Contracting Corp.  Giannetti has recently completed construction of the Jupiter Inlet Colony sewer/water/stormwater systems.  Work has begun and is scheduled to be substantially complete in 180 days.

Whispering Trails

Preliminary engineering report was completed by Mathews Consulting, Inc.

A Notice of Intent to Assess and contract for engineering services with Mathews Consulting has been approved by the Governing Board.

Estimated Schedule of Activities:

Design is Complete.
Permitting Complete – November, 2017
Bidding Complete – February, 2018
Construction Start – July, 2018
Construction Completion – May, 2019

Imperial Woods Low Pressure

Easements have been obtained and a Notice of Intent to Assess was filed in September, 2017.

The project is the #1 ranked project of the LRPI grant request for this year.  We are working with Legislators to obtain funding this session.  Residents are encouraged to contact Legislators also.

Island Country Estates-Martin County Low Pressure

Easements are being obtained and a Notice of Intent to Assess will be filed in July 2018.

Martin County-County Line Road

Owners notified July 2013.  Notice of Intent to Assess filed April 2018 with construction starting in May 2018.

8th Street

Owners notified January 2014.  Notice of Intent to Assess filed April 2018.

Chippewa Street

Owners notified January 2014.  Notice of Intent to Assess filed April 2018.

Olympus Drive, Juno Low Pressure

In house preliminary design is currently underway.

Peninsular Road Low Pressure

This neighborhood consists of four remaining houses on a peninsula into the Loxahatchee River south of Riverside Drive. The District Governing Board has approved a Notice of Intent to Assess which has been filed in the public records.

A Low Pressure sewer line has been extended to vacant properties on Peninsular Road.

SE Rivers Edge St. Low Pressure

A Notice of Intent to Assess was filed in March, 2014. The road is privately owned and maintained. This is not a lien on the property, it is only a notice to parties of any future land transaction of the proposed sewering.

Property owners have received a request for easements to the private road for installation of the sewer system. The request for easements under the current program is offered for a limited time only.

197th Place N Area

A Notice of Intent to Assess has been filed in the public record. This is not a lien on the property, it is only a notice to parties of any future land transaction of the proposed sewering.

Sewering has been delayed due to easement issues.